Do I need planning permission for a side extension?

In England, a side extension to a house is likely permitted development if the part beside the house is single storey, no more than 4 metres high and no wider than half the width of the original house. Anything bigger likely needs planning permission. On designated land (conservation areas, National Parks and so on) there is no right to extend beyond a side wall at all. Flats have no right. Article 4 directions and planning conditions can remove the right.

Check your address

The address matters because designated land removes the side extension right, and an Article 4 direction or a planning condition can take the right away.

For example, SW1A 2AA

The rules

  1. Height. Any part of the extension that goes beyond a side wall of the original house can be no more than 4 metres high. Schedule 2, Part 1, Class A, paragraph A.1(j)(i)
  2. One storey. Any part beyond a side wall must have a single storey. Schedule 2, Part 1, Class A, paragraph A.1(j)(ii)
  3. Width. Any part beyond a side wall can be no wider than half the width of the original house. Schedule 2, Part 1, Class A, paragraph A.1(j)(iii)
  4. Next to a road. It must not go beyond a side wall of the original house that fronts a highway. This matters on a corner plot. Schedule 2, Part 1, Class A, paragraph A.1(e)(ii)
  5. Near the boundary. If any part is within 2 metres of the boundary, the eaves can be no more than 3 metres high. Schedule 2, Part 1, Class A, paragraph A.1(i)
  6. Earlier extensions. The limits apply to the total enlargement, the new part together with any existing extension it joins, measured from the original house. Schedule 2, Part 1, Class A, paragraph A.1(ja)

Worked examples

Designated land and listed buildings

On article 2(3) land (conservation areas, National Parks, the Broads, areas of outstanding natural beauty and World Heritage Sites), the extension must not go beyond a wall forming a side elevation of the original house. A side extension there likely needs planning permission. The same applies to the total enlargement. The outside also cannot be clad in stone, artificial stone, pebble dash, render, timber, plastic or tiles. Schedule 2, Part 1, Class A, paragraph A.2(b)Schedule 2, Part 1, Class A, paragraph A.2(a)Schedule 2, Part 1, Class A, paragraph A.2(d) A listed building has no permitted development right to extend, and listed building consent is a separate consent. Ask the council.

Conditions and local removal of the right

The right does not apply to flats or maisonettes, or if a condition on the house's planning permission removes it. A council can also remove it with an Article 4 direction. Article 2(1), definition of dwellinghouseArticle 3(4)Article 4(1)

What this checker cannot see

It cannot see what the original house was, the exact line of your boundary, earlier extensions the council holds on record, or any listed building consent. It does not check building regulations or the Party Wall etc. Act 1996, which are separate.

What to do next

Enter your postcode above to see the constraints at your address. To get the council's written confirmation, apply for a lawful development certificate . We are preparing a paid report for your address, with the constraints, the limits for your project, the sources and the questions to ask the council.