Do I need planning permission for a ground or water source heat pump?

In England, a ground source or water source heat pump in the grounds of a house or block of flats is likely permitted development if it is a small system (a heat output of 45 kilowatts or less). The rights set no limits on size, number or position, and have no prior approval step. Article 4 directions and planning conditions can remove them. A heat pump that takes heat from the air is a separate question.

Check your address

The address matters because an Article 4 direction or a planning condition changes the answer.

For example, SW1A 2AA

The rules

There are two rights in Part 14. Class C covers a ground source heat pump. Class D covers a water source heat pump, where water is the collecting medium. A flat or maisonette is covered too. If you are not sure which kind you have, the answer is to ask the council. Schedule 2, Part 14, Classes C and D

  1. Where it goes. The pump must be within the curtilage of a house or block of flats, meaning its own grounds. If the pump or its pipes would be outside them, the answer is to ask the council. Schedule 2, Part 14, Class C, paragraph C (permitted development)Schedule 2, Part 14, Class D, paragraph D (permitted development)
  2. Small system only. The right covers microgeneration, which for heat means a plant with a capacity of 45 kilowatts thermal or less. A larger pump is not covered, so ask the council. Schedule 2, Part 14, Class C, paragraph C (microgeneration), with section 82(6) of the Energy Act 2004Schedule 2, Part 14, Class D, paragraph D (microgeneration), with section 82(6) of the Energy Act 2004

Beyond those two points, the classes set no limits on size, number or position, and no conditions. They have no prior approval route, so the answer is never prior approval.

Worked examples

Conditions on the house and local removal of the right

The right does not apply if a condition on the planning permission removes it, in which case you likely need planning permission. A council can also remove either right with an Article 4 direction. Article 3(4)Article 4(1)Article 4(1)

Listed buildings, conservation areas and other designated land

Classes C and D do not themselves set limits for these, so this checker has no rule for them. Listed building consent is a separate consent that permitted development never gives, so if the house is listed, ask the council before you start.

What this checker cannot see

It does not check digging, boreholes or trenches, licences to take water from the ground or a river or to discharge water (from the Environment Agency), land drainage, water rights, building regulations or listed building consent. These are outside planning permission and may still apply. It cannot see the heat output of your system, so it relies on the installer's specification.

What to do next

Enter your postcode above to see the constraints at your address. To get the council's written confirmation, apply for a lawful development certificate . We are preparing a paid report for your address, with the constraints, the limits for your project, the sources and the questions to ask the council.

Change log

  1. : First published.

Last updated 13 November 2026.