Checked against the law on 13 November 2026.
Do I need planning permission for ground-mounted solar panels?
In England, free-standing solar panels in the garden of a house are likely permitted development if the panels cover no more than 9 square metres, stand no higher than 4 metres (less near the boundary or a road), and the house is not a listed building or on a scheduled monument. In a conservation area where the panels are nearer a road than the house, or within 5 metres of the boundary on other protected land (a National Park, National Landscape, the Broads or a World Heritage Site), you likely need the council's prior approval of the appearance first. Article 4 directions and planning conditions can remove the right. Panels on a roof are a separate question.
Check your address
The address matters because a conservation area, a World Heritage Site, a listed building, an Article 4 direction or a planning condition changes the answer.
The limits
The right is Class B of Part 14. It covers solar panels that are not fixed to a building, for a small system that makes electricity or heat for the home (microgeneration). Flats and maisonettes have separate limits in the Order, so for those the answer is to ask the council. Schedule 2, Part 14, Class B, paragraph B.1(1) (block of flats)Schedule 2, Part 14, Class B (permitted development), Energy Act 2004, section 82(6)
- Height. Measured from the ground, the lowest limit that applies is the one that counts. The limit is 1 metre if any part is within 5 metres of the boundary and in front of the main wall of the house that faces the road. It is 2 metres if any part is within 5 metres of the boundary. In a conservation area it is 2 metres if any part is nearer a road or path along your boundary than the closest part of the house. In any other case it is 4 metres. Schedule 2, Part 14, Class B, paragraph B.1(2)(a), table row (i)Schedule 2, Part 14, Class B, paragraph B.1(2)(a), table row (ii)Schedule 2, Part 14, Class B, paragraph B.1(2)(a), table row (iii)Schedule 2, Part 14, Class B, paragraph B.1(2)(a), table row (iv)
- Area. The solar panels can have a surface area of no more than 9 square metres. Schedule 2, Part 14, Class B, paragraph B.1(2)(c)
- World Heritage Sites. In a World Heritage Site, the panels cannot go nearer a road or path along your boundary than the closest part of the house, and cannot go within 5 metres of the boundary. Schedule 2, Part 14, Class B, paragraph B.1(2)(b)(i)(aa)Schedule 2, Part 14, Class B, paragraph B.1(2)(b)(i)(bb)
- Plug-in solar. Plug-in solar cannot be fixed to a wooden fence, gate, wall or other kind of enclosure. Schedule 2, Part 14, Class B, paragraph B.1(2)(d)
Prior approval
Before you start, you must apply to the council for a decision on whether its prior approval is needed for the look of the panels, if either of these applies. First, the site is in a conservation area and any part is nearer a road or path along your boundary than the closest part of the house. Second, the site is in a conservation area, National Park, National Landscape, the Broads or a World Heritage Site and any part is within 5 metres of the boundary. The council has 56 days to decide. If it says nothing in that time you can go ahead, and you must build what you applied for. Schedule 2, Part 14, Class B, paragraphs B.2(aa)(i), (ab)Schedule 2, Part 14, Class B, paragraphs B.2(aa)(ii), (ab)
Worked examples
- A free-standing array of 6 square metres, 2.5 metres high, in the middle of a garden more than 5 metres from every boundary, at a house outside any conservation area, with none of the other problems below: it is within the height and area limits, so it is likely permitted development.
- An array of 12 square metres: over the 9 square metre limit, so it likely needs planning permission.
- An array 2.5 metres high with part of it within 5 metres of the boundary: over the 2 metre limit, so it likely needs planning permission.
Designated land, listed buildings and scheduled monuments
The right gives nothing in the grounds of a listed building or on a site designated as a scheduled monument. Where either applies, the panels likely need planning permission. Listed building consent and scheduled monument consent are separate consents that permitted development never gives. Conservation area and World Heritage Site limits are in the lists above. Schedule 2, Part 14, Class B, paragraph B.1(2)(b)(ii)Schedule 2, Part 14, Class B, paragraph B.1(2)(b)(iii)
Conditions
The panels must be sited, so far as practicable, to keep their effect on the look of the area as small as possible. They must be removed as soon as reasonably practicable when no longer needed. Schedule 2, Part 14, Class B, paragraph B.2(a)Schedule 2, Part 14, Class B, paragraph B.2(b)
Conditions on the house and local removal of the right
The right does not apply if a condition on the planning permission removes it. A council can also remove it with an Article 4 direction. Article 3(4)Article 4(1)
What this checker cannot see
It cannot see whether your system counts as microgeneration, how well the siting keeps its effect on the area small, or any listed building or scheduled monument consent. It does not check electrical safety, building regulations or a connection to the grid, which are separate.
What to do next
Enter your postcode above to see the constraints at your address. To get the council's written confirmation, apply for a lawful development certificate . We are preparing a paid report for your address, with the constraints, the limits for your project, the sources and the questions to ask the council.
Change log
- : First published.