Can I add a storey to my house without planning permission?
In England, for a detached, semi-detached or terraced house, the best answer is that adding one or two storeys likely needs prior approval from the council. You apply before you start, and you must wait for written approval. It is never simply permitted development. The right gives nothing in a conservation area, National Park, National Landscape, the Broads or a World Heritage Site, or on a site of special scientific interest, and it is only for houses built from 1 July 1948 to 28 October 2018. Flats and maisonettes are not covered.
Check your address
The address matters because a conservation area, a National Park, an Article 4 direction or a planning condition changes the answer.
The limits
The right is Class AA of Part 1. It permits one extra storey on a house of one storey, or up to two extra storeys on a house of two or more storeys, built immediately above the topmost storey. More than that likely needs planning permission. Schedule 2, Part 1, Class AA, paragraph AA(a), (b)Schedule 2, Part 1, Class AA, paragraph AA(b)
- Which houses. The right is for a house, not a flat or maisonette. A house made by converting an office, shop, farm building or similar under permitted development gets no right, so ask the council. A house built before 1 July 1948 or after 28 October 2018 likely needs planning permission. Article 2(1), definition of dwellinghouseSchedule 2, Part 1, Class AA, paragraph AA.1(a)Schedule 2, Part 1, Class AA, paragraph AA.1(c)
- Protected land. There is no right on a conservation area, National Park, National Landscape, the Broads, a World Heritage Site or a site of special scientific interest. Schedule 2, Part 1, Class AA, paragraph AA.1(b)(i)Schedule 2, Part 1, Class AA, paragraph AA.1(b)(ii)
- Used once. If storeys have already been added above the original house, there is no right. Schedule 2, Part 1, Class AA, paragraph AA.1(d)
- Total height. After the work, the highest part of the roof can be no more than 18 metres high. Schedule 2, Part 1, Class AA, paragraph AA.1(e)
- Rise in height. The highest part of the roof can rise no more than 3.5 metres above where it is now on a house of one storey, and no more than 7 metres on a house of more than one storey. Schedule 2, Part 1, Class AA, paragraph AA.1(f)(i)Schedule 2, Part 1, Class AA, paragraph AA.1(f)(ii)
- Joined houses. A house that is not detached can end up no more than 3.5 metres higher than the roof of the house it is joined to, or of every other house in its row. Schedule 2, Part 1, Class AA, paragraph AA.1(g)
- Ceiling height. A new storey can have a floor to ceiling height of no more than 3 metres, measured inside, and no higher than any storey in the main part of the house now. Schedule 2, Part 1, Class AA, paragraph AA.1(h)(i)Schedule 2, Part 1, Class AA, paragraph AA.1(h)(ii)
- Where it goes and how. New storeys go on the main part of the house, not a lower front, side or rear extension. The finished house cannot have support structures visible on, or fixed to, the outside. The only ground works allowed are strengthening the existing walls or foundations inside the garden. Schedule 2, Part 1, Class AA, paragraph AA.1(i)Schedule 2, Part 1, Class AA, paragraph AA.1(j)Schedule 2, Part 1, Class AA, paragraph AA.1(k)
- Chimneys and flues. Class AA does not mention chimneys, flues or soil and vent pipes, so if the work includes one, ask the council. Schedule 2, Part 1, Class AA (the Order is silent on chimneys, flues and soil and vent pipes)
Prior approval
Before you start, you must apply to the council for prior approval. It looks at the effect on neighbours (overlooking, privacy and loss of light), the outside look of the house (the front and any side facing a road or path), air traffic and defence assets, and, near one, a protected London view. You must wait for its written notice of approval, and a fee applies. Schedule 2, Part 1, Class AA, condition AA.2(3)(a)
What to send
- A written description of the work.
- A plan with north marked, showing the site and the work.
- Plans of the existing and proposed elevations, showing the windows.
- A construction management report: the hours you will work, and how you will limit noise, dust, vibration and traffic for neighbours.
The council writes to each adjoining owner or occupier, who have at least 21 days to comment, and it can refuse an application that does not meet the limits and conditions. Schedule 2, Part 1, Class AA, paragraphs AA.3(2), (5), (13)Schedule 2, Part 1, Class AA, condition AA.2(3)(b)
Worked examples
- A detached two-storey house built in 1995, outside any conservation area or other protected land, with one new storey that raises the roof by 3 metres to under 18 metres in total, ceiling height 2.4 metres, no side windows and the same roof pitch: it is within the limits, so it likely needs prior approval.
- The same house with the roof raised by 8 metres: over the 7 metre limit for a house of more than one storey, so it likely needs planning permission.
Conditions
- The outside materials must be similar in appearance to the existing house, the new storeys cannot have a window in a side wall or side roof slope, and the roof pitch of the main part must stay the same. Schedule 2, Part 1, Class AA, condition AA.2(2)(a)Schedule 2, Part 1, Class AA, condition AA.2(2)(b)Schedule 2, Part 1, Class AA, condition AA.2(2)(c)
- After the work, the house must be used only as a home, apart from uses that go with living there. Schedule 2, Part 1, Class AA, condition AA.2(2)(d)
- You must finish within 3 years of the date prior approval is given, then tell the council in writing as soon as you reasonably can, with your name, the address and the date of completion. Schedule 2, Part 1, Class AA, condition AA.2(3)(c) to (e)
Conditions on the house and local removal of the right
The right does not apply if a condition on the planning permission removes it. A council can also remove it with an Article 4 direction. Listed building consent is a separate consent that permitted development never gives, so ask the council first if the house is listed. Article 3(4)Article 4(1), direction removing Class AA (code 1AA)
What this checker cannot see
It cannot see how the council will judge the effect on neighbours or the look of the house, whether your house was converted under permitted development, or whether the structure can carry the extra storeys. It does not check building regulations or structural safety, which are separate.
What to do next
Enter your postcode above to see the constraints at your address. To get the council's written confirmation, apply for a lawful development certificate , or apply for prior approval as above. We are preparing a paid report for your address, with the constraints, the limits for your project, the sources and the questions to ask the council.